Projects & installations

What Northline is building and has delivered at Linden Commercial. 1 active · 4 completed.

Loading-dock camera coverage on the Northline monitoring wall
Active projectIn progress

Loading dock access control upgrade

Upgrading readers, the dock door controller, and camera coverage across the loading dock and storage corridor.

Equipment procurement38% complete

Project lead

Maya O.

Started

May 20, 2026

Target completion

July 8, 2026

The loading dock and storage corridor are moving to current-generation readers with auto-expiring credentials and tenant-hour schedules, alongside a new door controller and refreshed camera coverage. The design maps badge access to delivery windows so the dock stays secure outside of scheduled carrier slots. Work is staged around tenant hours to avoid disruption.

View installed devices

Progress photos

Access reader staged for installation
Access reader staged for installation
Network cabinet
Network cabinet
Camera coverage review
Camera coverage review

Milestones

  1. Site assessment

    May 20, 2026

  2. Design review

    May 26, 2026

  3. Equipment procurement

    In progress

    May 30, 2026

    Long-lead reader controllers on order; cameras in stock.

  4. Installation

  5. Commissioning

  6. Final handover

Recent updates

  1. Procurement underway; long-lead reader controllers ordered.

    May 30, 2026 · Maya O.

  2. Design review approved; badge schedule mapped to tenant delivery hours.

    May 26, 2026 · Maya O.

  3. Site assessment completed across the dock and storage corridor.

    May 20, 2026 · Maya O.

Completed projects

Refreshed core switching and patch panel

Core network refresh

Completed

Completed October 12, 2025

48-port core, distribution switching, and roof access points replaced over a maintenance window with no tenant downtime.

Modernized lobby access reader

Lobby and stair reader modernization

Completed

Completed May 22, 2025

Lobby and stair readers upgraded with auto-expiring credentials and tenant-hour schedules.

EV charging bay

Parking EV charger deployment

Completed

Completed August 5, 2024

Four Level 2 bays installed with a controller holding total charger draw under the building limit.

Building-wide cameras and access commissioned

Building systems commissioning

Completed

Completed December 18, 2023

Cameras, access, network, and EV commissioned building-wide before the first tenants moved in.